On GoingProject Client Location Duration Status
TakeharaThermal Power Plant STEP Eng. Japan 2018.06. ~ On Going
IPA50KTA Expansion Project SERVEONE Korea 2018.06. ~ On Going
IADC Project STEP Eng. Indonesia 2018.04. ~ 2018.05. Complete
KURIDA WWT Project STEP Eng. China 2018.03. ~ 2018.04. Complete
STEPAUTO CAD PLANT (3D Model) STEP Eng. Japan 2018.03. ~ 2018.04. Complete
W-Project Hanwha Korea 2018.03. ~ On Going
NH3 Storage Facilities Improvement Project (Y-Project) Hanwha Korea 2018.03. ~ On Going
K-10(PVC) Project Hanwha E&C Korea 2018.02. ~ On Going
Pulverization (Off-Spec) Improvement Project Orion Engineered Carbons, Korea Korea 2018.02. ~ On Going
Toyo BST Expansion Project Toyo Eng. Korea Thailand 2018.01. ~ 2018.06. Complete
C3 (ConvertingCB) Project Orion Engineered Carbons, Korea Korea 2018.01. ~ 2018.04. Complete
S1/S3Debottlenecking Project Orion Engineered Carbons, Korea Korea 2017.12. ~ 2018.04. Complete
Electric Receiving Fac. Expansion Project Hansol Chemical Korea 2017.10. ~ 2018.04. Complete
Production FacilityExpansion Project Hansol Chemical Korea 2017.09. ~ 2018.04. Complete
PyeongTakPhase4Skid & Vessel Project STEP Eng. Korea 2017.09. ~ On Going
L224 Relocation Project Air Products Korea Korea 2017.09. ~ 2018.04. Complete
CAP NPE Project Toyo Eng. Korea Korea 2017.08. ~ 2018.04. Complete
C1/C2Silo Improvement Project Orion Engineered Carbons, Korea Korea 2017.04. ~ 2018.04. Complete
Hanwha Total NCC Project (Piping) Hanwha E&C Korea 2017.05. ~ 2018.03. Complete
NCC Side Cracker Project (Cas) Hanwha E&C Korea 2017.04. ~ 2018.05. Complete
Power Plant WWT Project STEP Eng. Korea 2017.04. ~ On Going
Tang-jeongT7 Retrofit & TJ5 Project Air Products Korea Korea 2017.03. ~ 2017.10. Complete
C1 Project Orion Engineered Carbons, Korea Korea 2017.03. ~ 2017.08. Complete
S4 Project Orion Engineered Carbons, Korea Korea 2017.03. ~ 2017.04. Complete
P-Phase#2Project Air Products Korea Korea 2016.12. ~ On Going
KANDY City Waste Water Supply Project STEP Eng. China 2016.11. ~ 2017.03. Complete
ARO#2 De-Bottlenecking Project Hanwha E&C Korea 2016.09. ~ 2017.06. Complete
C2 Upgrade Detail Engineering Orion Engineered Carbons, Korea Korea 2016.08. ~ 2017.04. Complete
Jeonui Co2 Storage Tank Wonic Materials Korea 2016.08. ~ 2017.08. Complete
KCC Kimcheon O2 VSA Air Products Korea Korea 2016.07. ~ 2016.10. Complete
Anyang Co-Generation Plant No.2-1 KOGAS-Tech. Korea 2016.03. ~ On Going
Yeocheon Ne-He Mixture Gas Collection Equipment Deasung Industrial Gas Korea 2016.02. ~ 2016.12. Complete
SCK 100HN Air Products Korea Korea 2016.02. ~ 2016.05. Complete
JangMoon Natural Gas LNG plant piping design and engineering services (Vent Stack ) KOGAS-Tech. Korea 2015.06. ~ 2016.08. Complete
Inchon Terminal separate design engineering services KOGAS-Tech. Korea 2015.05. ~ 2018.05. Complete
ASPEX Steam Turbine Expansion EPC Project Dowha Eng. Indonesia 2015.03. ~ 2015.07. Complete
TGPC – GSU PROJECT Toyo Eng. Korea Turkmenistan 2015.03. ~ 2016.07. Complete
Production Base Ⅵ Zone #21~23 Tank in Incheon City (Steel Structure & Outer Tank ) KOGAS-Tech. Korea 2015.01. ~ 2016.01. Complete
TGPC – PP PROJECT Toyo Eng. Korea Turkmenistan 2014.10. ~ 2016.07. Complete
LNG Piping & Vent Stack – (Wirye) KOGAS-Tech. Korea 2014.09. ~ 2016.08. Complete
Boryung LPG Terminal LNG Storage Tank KOGAS-Tech. Korea 2014.07. ~ 2016.12. Complete
Daegu Municipal Waste-Energy Private Investment Project DOWHA Eng. Korea 2013.06. ~2013.09. Complete
N3 Project Hanwha E&C Korea 2013.01. ~ 2013.11. Complete
KPIC EOG Project Toyo Eng. Korea Korea 2013.01. ~ 2015.05. Complete
Hangzhou LNG Terminal LNG Storage Tank(Steel Structure) KOGAS-Tech. China 2012.12. ~ 2016.03. Complete
Hangzhou LNG Terminal LNG Storage Tank (Outer Wall) KOGAS-Tech. China 2012.11. ~ 2016.03. Complete
Boryeong LNG Terminal LNG Storage Tank (Steel Structure) KOGAS-Tech. Korea 2012.08. ~2016.12. Complete
KTH BIOMASS FIRED POWER PLANT Dowha Eng. Indonesia 2011.10. ~ 2013.03. Complete
HCC Polysilicon Project Hanwha E&C Korea 2011.06. ~ 2012.12. Complete
HCC EVA Project Hanwha E&C Korea 2010.06. ~ 2012.11. Complete
LG BR Expansion Project Toyo Eng. Korea Korea 2010.06. ~ 2010.10. Complete
Singapore LNG Terminal LNG Storage Tank (Outer Wall) KOGAS-Tech. Singapore 2010.04. ~ 2014.03. Complete
Singapore LNG Terminal LNG Storage Tank (Steel Structure) KOGAS-Tech. Singapore 2010.04. ~ 2014.03. Complete
Samcheok LNG Terminal #1~4 LNG Storage Tank (Outer Wall) KOGAS-Tech. Korea 2009.04. ~ 2015.08. Complete
CA No4 Ulsan Project Hanwha E&C Korea 2008.04. ~ 2009.12. Complete
GUNJANG COGENERATION POWER PLANT Hanwha E&C Korea 2008.03. ~ 2011.01. Complete
DCSS Project (Phase-2) Toyo Eng. Korea Korea 2007.10. ~ 2008.04. Complete
CES Thermal Power Plant at GWANGMYEONG Daewoo Eng. Korea 2007.09. ~ 2010.05. Complete
KPAⅢ Revamp Project Daewoo Eng. Korea 2007.12. ~ 2008.09. Complete
STC OCU Project SW E&C Korea 2007.04. ~ 2008.05. Complete
B-1 (Biodiesel) Project SW E&C Korea 2007.04. ~ 2008.02. Complete
D-PROJECT (PMMA) SW E&C Korea 2007.04. ~ 2008.01. Complete
Supply Energy at GOYANG Go Yang City Korea 2007.03. ~ 2008.01. Complete
GDC Project Daewoo Eng. Korea 2007.02. ~ 2009.03. Complete
Thermal Power Plant at YEOCHON Daewoo Eng. Korea 2007.10. ~ 2008.12. Complete
RW Project SW E&C Korea 2007.10. ~ 2008.08. Complete
154KV T/L of Co-generation Power Plant Woo One E&C Korea 2006.08. ~ 2009.01. Complete
Tiger-Project SW E&C Korea 2006.06. ~ 2009.01. Complete
F-1 Project SW E&C Korea 2006.06. ~ 2008.08. Complete
Grouped Supply Energy KWANGMYOUNG Daewoo Eng. Korea 2006.06. ~ 2007.06. Complete
Sakhalin BS-II Project KOGAS-Tech. Korea 2006.05. ~ 2008.07. Complete
KC PROJECT SW E&C Korea 2006.04. ~ 2008.01. Complete
YNCC ISBL/OSBL Project (Power Block) Hanwha E&C Korea 2006.02. ~ 2007.04. Complete
DCSS Project Toyo Eng. Korea Korea 2007.10. ~ 2008.04. Complete
KCC S2 PROJECT Hanwha E&C Korea 2005.09. ~ 2006.11. Complete
Korea Bolt Factory Branch at CHUNGJU Humantec Korea 2005.01. ~ 2007.02. Complete
Sewerage Wok Station at NA JU SAMAN Korea 2004.10. ~ 2006.01. Complete
NANO Integrate FAB Center Sewerage Wok Station of KIST Humantec Korea 2004.08. ~ 2006.11. Complete
Second EGL Expansion Project Union Steel Korea 2004.08. ~ 2006.10. Complete
POLYOL Expansion project of BASF Korea at Ul-san, Korea Hanwha E&C Korea 2004.07. ~ 2006.11. Complete
SIAS Corporation O Chang Factory Branch Humantec Korea 2004.06. ~ 2006.09. Complete
Heat Source Facility at YONGIN DONGBAEK Korea District Heating Corp. Korea 2004.04. ~ 2006.08. Complete
Digital Media City CES at Sang Am Korea District Heating Corp. Korea 2004.03. ~ 2005.06. Complete
PO SUNG Factory of Youlchon Chemical Humantec Korea 2004.03. ~ 2005.04. Complete
#3,4th of Industrial Complex of FGD at DAEJEON Humantec Korea 2003.11. ~ 2004.09. Complete
WASHING BASIN Expansion Construction at PYEONGTAEK Humantec Korea 2003.11. ~ 2005.01. Complete
Landfill Works & Related Facility SunJin Eng. Korea 2003.07. ~ 2005.08. Complete
Final Sewerage Work Station of Sanitize Facility Dong Myoung Korea 2003.07. ~ 2006.06. Complete
FGD Facility of Thermal Power Plant Unit 5 & 6 at DANG JIN Hanwha E&C Korea 2003.06. ~ 2005.11. Complete
LPG & Steam Supply Facility at Dae-Jook Complex MAC Eng. Korea 2003.06. ~ 2005.11. Complete
North River Distributing Reservoir at YEOJU-GUN Dong Myoung Korea 2003.04. ~ 2004.07. Complete
Kalox Project Toyo Eng. Korea Korea 2003.02. ~ 2004.04. Complete
S-Oil R2R Revamping Project Toyo Eng. Korea Korea 2003.02. ~ 2004.12. Complete
Tank Terminal Installation at Mang-woo Mt. Jung Nak Dist. Korea 2002.11. ~ 2003.04. Complete
Second Drainage Facility project Jung Nak Dist. Korea 2002.11. ~ 2004.09. Complete
FGD Facility of Thermal Power Unit 5 & 6 at DANGJIN Hanwha E&C Korea 2002.11. ~ 2005.01. Complete
Acetonitrile (MeCN) project Toyo Eng. Korea Korea 2002.11. ~ 2004.10. Complete
POLYOL Expansion project of BASF Korea at Ul-san, Korea Hanwha E&C Korea 2002.07. ~ 2004.03. Complete
MDI Expansion structural part of BASF Hanwha E&C Korea 2002.05. ~ 2004.02. Complete
MDI Pipe rack project of BASF Hanwha E&C Korea 2002.02. ~ 2003.12. Complete
Middle East
Project Client Location Duration Status
Oman SAP Project (Steel Structure) Hanwha E&C Oman 2016.03. ~ 2016.07. Complete
KNPC Al-Zur New Refinary Project Hanwha E&C Kuwait 2015.12. ~ 2018.05. Complete
Saudi Arabian Petroleum Coke Calcining PROJECT Hanwha E&C Saudi Arabia 2015.05. ~ 2016.02. Complete
Aramco RTR CFP Hanwha E&C Saudi Arabia 2014.10. ~ 2015.01. Complete
PAP PROJECT Hanwha E&C Saudi Arabia 2014.04. ~ 2016.09. Complete
JRTP Package14 Project Hanwha E&C Saudi Arabia 2013.01. ~ On Going
SAUDI Cryogenic Tank Farm Project KOGAS-Tech. Saudi Arabia 2012.03. ~ 2015.08. Complete
ABEOP2 PROJECT Toyo Eng. Korea Saudi Arabia 2012.02. ~ 2014.04. Complete
MARAFIQ STG UNITS 5 & 6 PROJECT – Fuel Supply (HFO) Hanwha E&C Saudi Arabia 2011.12. ~ 2013.08. Complete
Yanbu2 Project Hanwha E&C Saudi Arabia 2011.06. ~ 2014.02. Complete
MARAFIQ STG UNITS 5&6 PROJECT Hanwha E&C Saudi Arabia 2010.10. ~ 2012.07. Complete
Samra Thermal Power Station Phase III Project Hanwha E&C Jordan 2009.02. ~ 2009.03. Complete
Sabiya CCGT Project Hundai Heavy Ind. Kuwait 2009.09. ~ 2012.06. Complete
Ma’aden Phosphate Project Hanwha E&C Saudi Arabia 2008.02. ~ 2010.06. Complete
Safra II NG Expansion Project Hanwha E&C Saudi Arabia 2007.04. ~ 2008.12. Complete
Africa
Project Client Location Duration Status
Algeria SCPP Project (BISKRA) Hanwha E&C Algeria 2013.12. ~ 2016.12. Complete
EEPE Project Toyo Eng. Korea Egypt 2013.08. ~ 2015.05. Complete
Arzew Refinery Project Hanwha E&C Algeria 2009.03. ~ 2011.12. Complete
Madagascar Ammonia Plant Project (Civil & Piping) KOGAS-Tech. Madagascar 2008.06. ~ 2010.07. Complete
Europe
Project Client Location Duration Status
PAVLODAR OIL Chemistry Refinery Upgrading Phase 1 Global Engineering Technology Kazakhstan 2014.10. ~ 2015.07. Complete
PAVLODAR OIL Chemistry Refinery Upgrading FEED Global Engineering Technology Kazakhstan 2014.02. ~ 2014.04. Complete
PAVLODAR Oil Chemistry Refinery Upgrading Early Phase Global Engineering Technology Kazakhstan 2013.12. ~ 2015.04. Complete
Sakhalin 1 Export Terminal Project Toyo Eng. Korea Russia 2005.01. ~ 2007.03. Complete
America
Project Client Location Duration Status
Toyo YPE FEED EarlyWork Project (Exxon Mobile & SABIC) Toyo Eng. Korea U.S.A 2017.09. ~ 2018. 06. Complete
Panama Costa Norte LNG Terminal LNG Tank(Tank) KOGAS-Tech. Panama 2016.04. ~ On Going
Panama Costa Norte LNG Terminal LNG Tank(Steel Structure) KOGAS-Tech. Panama 2016.04. ~ On Going
SASOL LLDPE PROJECT (BRIDGE WORK) Toyo Eng. Korea U.S.A 2013.05. ~ 2013.08. Complete
Sabiya CCGT Power Station Project (Bid design) Hyundai Heavy Industries U.S.A 2009.09. ~ 2012.11. Complete
Mexico Manzanillo LNG Terminal Storage Tank KOGAS-Tech. Mexico 2008.07. ~ 2011.09. Complete
Brazil Cabiunas Gas Plant Project (CGP) Toyo Eng.Korea Brazil 2003.02. ~ 2005.05. Complete